EGL successfully performed the movement of construction equipment for the New Light Rail Line Project in Egypt.

Door-to-Door Project Service (EGL – Kadmar Group)

Project Information

A French-Egyptian Consortium  obtained an Egyptian Ministry of Transport contract for overhaul including the construction of a light rail track that will link Cairo with the 10th of Ramadan railway. Last year, the government launched a tender to revamp the line as part of the ongoing EGP 56 billion plan to overhaul the national railways by purchasing new railcars, improving junctions, building new lines, and automating signaling systems.

Project Execution

On the 01st August 2020 Egyptian Global Logistics (EGL), subsidiary of KADMAR GROUP received a Door-to-Door RFQ to mobilize 5,000 cu.m of locomotives heavy equipment’s (Locomotive Diesel, Tamping Machines, Hopper Wagon, Wagon Flat & Regulator machines) from the KSA (El-Dammam port) to Egypt (Adabiya port).

EGL immediately opened a hotline (operation connections) in order to arrange all necessary operations in the KSA and represent us in front of all utilities, authorities, Saudi Customs and the port terminal.

Scope of Work in the KSA

  1. Handling origin service at the site in Dammam.
  2. Route and Site Survey to El-Dammam port.
  3. Cranes with the loading capacity of up to 600 tons supply for the site.
  4. In-Land Transportation from 3 different sites to the loading port Damam.
  5. Handling in the port, Customs Clearance and Stevedoring.
  • Chartering scope: a geared vessel hire.

 

  • Scope of Work in Egypt
  1. Vessel berthing arrangement by coordination with Kadmar shipping Co.(ship agent).
  2. Route and Site Survey up to Abu-Rawash workshop.
  3. Handling in the port, Customs Clearance and Stevedoring.
  4. Arranging all permits needed to get Road Permits from utilities, Especially Road and Bridges Authority, as EGL succeeds in getting Consultant report due to cross El-Moneib River Nile bridge with Total Weight 180 tons.
  5. In-Land Transportations from Adabiya port to Abu-Rawash workshop.

 

In parallel and before release cargo from Adabiya port the JV had requested us to mobilize more than 25 units (Total 3,750 cbm) locomotives equipment from Abu-Rawash workshop to 3 different workshops (Minia El-Kamah, Badr LRT, and Al Qassaseen) to guarantee enough space to offload Adabiya cargo on rails after getting permits from ENR (Egyptian National Railways) to stop train traffic in Abu-Rawash Workshop.

EGL (Kadmar Group) achieved this success through careful planning and strong connections in the KSA, especially with our KSA partner without sacrificing safety aspects to meet clients’ demands.

Log In

Privacy Overview
thlg_new_logo_200.jpg

This website uses cookies so that we can provide you with the best user experience possible. Cookie information is stored in your browser and performs functions such as recognising you when you return to our website and helping our team to understand which sections of the website you find most interesting and useful.

Necessary

Strictly Necessary Cookie should be enabled at all times so that we can save your preferences for cookie settings.

Analytics

This website uses Google Analytics to collect anonymous information such as the number of visitors to the site, and the most popular pages.

Keeping this cookie enabled helps us to improve our website.