Heavy Lift News <> New Abu Qir Power Plant Substation.

Location:  New Abu Qir Substations, Alexandria
Client:     SIEMENS Technologies SAE  
EGL scope of work:  Jacking and Skidding of three transformers
                           
On the 27th January 2020 Egyptian Global Logistics (EGL), subsidiary of KADMAR GROUP completed jacking/skidding of 3 transformers (116 tons each) for SIEMENS in Abu Qir Substations.  
 
The site was located about 60 km from Alexandria city. It was a quite challenging operation which was performed and completed despite the difficult conditions. One of the most difficult was that the transformers had to be rotated 90 degrees before being installed on the foundations. Operation area was only 6.5 meters (width) without ground pulling eyes.
 
Thanks to EGL Project Team for cooperation. EGL continues to impress the market with the well trained staff along with the latest fleet equipment and technology in Egypt. EGL achieved this success through careful planning without sacrificing safety aspects.

Log In

Privacy Overview
thlg_new_logo_200.jpg

This website uses cookies so that we can provide you with the best user experience possible. Cookie information is stored in your browser and performs functions such as recognising you when you return to our website and helping our team to understand which sections of the website you find most interesting and useful.

Necessary

Strictly Necessary Cookie should be enabled at all times so that we can save your preferences for cookie settings.

Analytics

This website uses Google Analytics to collect anonymous information such as the number of visitors to the site, and the most popular pages.

Keeping this cookie enabled helps us to improve our website.