Armando  Lee      Wed, 27/10/2021

Tradelossa recently performed one of the most important operations for the month of October,
hauling a 245 tons transformer, Parting from the northern state of Nuevo León, Mexico, and
delivered at one of the most important wind farms within the state of Coahuila, Mexico.


Our story begins in April of 2021, Tradelossa had the request of storing a transformer inside their
installations at Apodaca, Nuevo Leon, the cargo’s dimensions included 10.37 meters in length,
4.08 meters of width, 5.18 meters of height, and a total weight of 245 tons.


Tradelossa stored and secured the cargo for about 5 months, however, for this project’s scope
hauling and rigging services were also requested, and so during the next month’s Tradelossa carry
out with multiple visits at site and the different key points of the selected route for this project,
preparing the terrain and implementing multiple land and road modifications within the
windfarm’s territory in order to prepare the installations for the cargo’s arrival, setting up a full
program, permitting, and schedule for the Cargo’s delivery and rigging operations.


The component was transported using a 4.5 meter 12- axle + Deck hydraulic Configuration, (Six
axles on front of the Deck and six axles on the back of the Deck) This configuration allowed our
team to perform the transportation of the 245 tons transformer through the northern states of
Mexico, traveling 284 kilometers from point of departure to site point’s main access.


During our previous visit to the site point, Tradelossa engineering team realized that in order to access
and carry out the cargo throughout the windfarm’s territory. The piece had to pass through
15 kms of steep terrain that could compromise the piece’s integrity.


With that in mind, our team of professionals designated Six Prime Movers for this sole project to
perform the titanic task of moving uphill 245 tons throughout 15 kms of both irregular and steep
terrain, once the cargo arrived at its designated point, our rigging team carefully unloaded the
component and prepared the piece for its future installation and use in their installations.


With about 300 kms traveled all services and operations were executed within the period of three
and a half days, making this project a complete success, accomplishing all of our client’s
expectations, and accomplishing all of our company’s High-Quality standards.

 

 